FIDIC 1999 Sub-Clause 20.1: the 28-day notice of claim

FIDIC 1999 Sub-Clause 20.1: the 28-day notice of claim

Sub-Clause 20.1 of the FIDIC 1999 Conditions of Contract is one of the most important – and most often neglected – provisions of a construction contract. It decides whether the Contractor keeps any right to an extension of time and additional payment at all.

What Sub-Clause 20.1 says

If the Contractor considers himself entitled to an extension of the Time for Completion or to additional payment, he must give notice to the Engineer describing the event or circumstance giving rise to the claim “as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance”.

The consequence of missing the deadline is severe: the Time for Completion is not extended, the Contractor is not entitled to additional payment and the Employer is discharged from liability in connection with the claim. A fully detailed claim with supporting particulars should follow within 42 days after the Contractor became aware (or should have become aware) of the event or circumstance – or within another period approved by the Engineer.

How the English courts read it

FIDIC disputes rarely reach national courts – they are usually decided by DABs and arbitral tribunals in private. That makes the judgment of the English Technology and Construction Court of 16 April 2014 in Obrascon Huarte Lain SA v Her Majesty’s Attorney General for Gibraltar, [2014] EWHC 1028 (TCC) (Akenhead J), concerning a FIDIC Yellow Book contract, all the more important. The court confirmed that the Sub-Clause 20.1 notice is a condition precedent, but stated (paragraph 312):

“I see no reason why this clause should be construed strictly against the Contractor and can see reason why it should be construed reasonably broadly, given its serious effect on what could otherwise be good claims for instance for breach of contract by the Employer.”

The judgment also indicates that the notice does not have to take any particular form but must be recognisable as a claim, and that the 28 days run from when the Contractor became or should have become aware of the event or circumstance – for delay, at the earliest when the delay has actually occurred.

Polish law: a contractual time bar, not limitation

In Poland it was long debated whether Sub-Clause 20.1 breaches Article 119 of the Civil Code, which prohibits shortening limitation periods. In its judgment of 23 March 2017, case no. V CSK 449/16, the Polish Supreme Court held that it is a time limit of a different kind:

„Termin przewidziany w omawianej klauzuli jest zatem umownym terminem notyfikacyjnym, w czasie którego należy zawiadomić drugą stronę o określonych okolicznościach, pod rygorem utraty określonych uprawnień.” (“The time limit provided for in this clause is therefore a contractual notification period within which the other party must be notified of certain circumstances, under pain of losing certain rights.”)

The Court based the validity of such a clause on freedom of contract (Article 353¹ of the Civil Code) and followed the same line in its judgment of 17 March 2022, case no. II CSKP 217/22. The effectiveness of the time bar is, however, assessed in relation to the specific claim – it is not an automatic bar in every case.

In practice: how not to lose a claim

  • Keep a register of events and notices from day one on site.
  • Notify promptly – better too early than after 28 days.
  • Title the letter clearly: “Notice of Claim under Sub-Clause 20.1” and describe the event.
  • Check the Particular Conditions – Polish contracts often shorten the periods (e.g. to 14 days).
  • Keep contemporary records and observe the 42-day period for the fully detailed claim.

Next article: Sub-Clause 20.2 – appointment of the Dispute Adjudication Board (DAB).


Author: Krzysztof Chabier, PMC Silesia. This article is based on many years of professional experience, projects managed by PMC Silesia and publicly available information.